ST. LOUIS COUNTY, Mo. — Missouri utility regulators have approved an agreement covering three Ameren Missouri battery-storage projects, including a 95-megawatt facility planned at the retired Meramec power plant in St. Louis County.
The Missouri Public Service Commission approved the agreement Oct. 21 with conditions addressing safety, costs, construction progress and permitting. The other battery projects are a 200-megawatt facility at Ameren’s Audrain Energy Center and a 250-megawatt facility in Lincoln County.
The commission also approved related plans for a Lincoln County switching station and solar projects in Audrain and Stoddard counties.
Under the agreement, Ameren must file quarterly reports on construction milestones, permits, costs, delays and potential effects of legislative or executive actions. The utility also must notify the commission if a project’s total cost changes by more than 15% from the applicable base or risk-adjusted estimate and explain efforts to control the increase.
Safety conditions require site-specific hazard information, environmental response procedures and compliance with the National Fire Protection Association standard for stationary energy storage. Ameren also must provide copies of state, federal and local permits obtained for each battery project.
The Office of the Public Counsel, which represents utility customers, did not sign the agreement but did not object, according to the commission.
The full decision and case link are available through the Missouri Public Service Commission.
Featured image: A technician works on energy storage equipment in an illustrative stock photograph. Photo by Elite Power Group/Pexels. The image does not depict an Ameren Missouri project.